Surat-Bilimora bullet train section gets electrified, signalling due by January

Source: IANS LIVE ·

Picture chosen by PropShort, not the publisher’s. Image credits

Electrification of the Surat-Bilimora stretch is complete, enabling signalling work to finish by January 2027 before trial runs begin in May. The B-28 train, tested at double atmospheric pressure, will operate on this 50-km segment of the Mumbai-Ahmedabad corridor. This phase precedes the Ahmedabad-Vapi target of late 2027 and Thane services by 2029.