Builder took Rs 13.10 lakh, didn't finish flats. Now the town planner must.
A consumer commission has ordered the Senior Town Planner, Faridabad, to complete the stalled SRS Affordable Group Housing Project in Palwal's Sector-6 and hand over flats, after builder SRS Real Estate Ltd failed to deliver. Kamlesh Sharma, who paid Rs 13.10 lakh for a 2 BHK flat, will get possession.
Key points
- Kamlesh Sharma booked a 2 BHK flat in SRS Affordable Group Housing, Sector-6, Palwal, in 2011.
- She was allotted flat no. 702, later changed to 504 in August 2014 after a site plan change.
- She deposited Rs 13.10 lakh; builder promised possession in 3 years 6 months but didn't deliver.
Why it matters
The practical property angle is approval timelines, compliance risk, and how the decision may affect buyers, builders, or local authorities.
Read the full report on Amar Ujala.