Ejipura flyover: 2017 start, 2019 deadline, 2026 order for five piers.
Bengaluru's Ejipura flyover, started in 2017, has missed its 2019 deadline and faces fresh delays. After Simplex's contract was terminated in 2022, BSCPL took over in 2023, but land acquisition and tree-removal objections persist. In January 2026, the civic chief directed work on five portal piers to begin.
Key points
- BBMP issued work order for Ejipura flyover on May 4, 2017, with a November 2019 completion deadline
- Delays due to traffic police clearances, blasting permits, land acquisition, and pandemic labour issues
- Simplex's contract terminated in March 2022 after financial troubles; BBMP spent Rs 75 crore, forfeited Rs 10.16 crore deposit, imposed Rs 2.5 crore penalty