Builder wanted 6 months COVID relief. RERA gave 4, plus 10.95% interest.
Punjab RERA has allowed a Zirakpur builder only four months of COVID-19 relief, not the six it sought, and ordered it to pay 10.95% annual interest to allottee Arvind Kumar Pal. Pal had paid over 95% of the flat's price in Sushma Valencia but faced delayed possession. The Authority rejected the developer's force majeure plea, citing a tribunal decision.
Key points
- Punjab RERA granted a Zirakpur builder four months of COVID-19 relief, not the six months it requested.
Why it matters
The practical property angle is approval timelines, compliance risk, and how the decision may affect buyers, builders, or local authorities.
Read the full report on tribuneindia.