Metro work began in 2018. Eight years on, Lines 4 and 6 are still unfinished.
Buyers and commuters waiting for Mumbai Metro Lines 4 and 6 face continued delays nearly eight years after work started, with neither corridor ready for service. Green Line 4 trials began in September 2025, yet incomplete stations have postponed any partial opening until November 2026.
Key points
- MMRDA's August 31, 2026 progress report shows Line 4 pier construction at 95%, U-girder erection at 94%, and deck-slab work at 92%.