NH-68 was due in March 2025. Now it's March 2027. 87% done.
NH-68's 76.94 km Patan-Gozariya highway, contracted to Vagad Infra Projects-Rachna Infrastructure JV for Rs 741 crore, is 26 months behind schedule. 87% work is done; the fourth deadline extension pushes completion to March 2027. Delays stem from forest clearance, land disputes, a JV financial conflict, and mineral department action, affecting commuters.
Key points
- NH-68 Patan-Gozariya stretch (76.94 km) contracted at Rs 741 crore; originally due March 2025, now fourth extension to March 2027.
- 87% work complete; remaining 13% to be done by March 2027; delay of about 26 months.
- Delays caused by forest clearance delay, land acquisition cases, JV financial dispute, and mineral department action.