NH-68 was due in March 2025. Now it's March 2027. 87% done.

Source: Divya Bhaskar ·

Picture chosen by PropShort, not the publisher’s. Image credits

NH-68's 76.94 km Patan-Gozariya highway, contracted to Vagad Infra Projects-Rachna Infrastructure JV for Rs 741 crore, is 26 months behind schedule. 87% work is done; the fourth deadline extension pushes completion to March 2027. Delays stem from forest clearance, land disputes, a JV financial conflict, and mineral department action, affecting commuters.