Most-built stretch of Delhi-Amritsar-Katra expressway is 94.14% done. Cost still rose.
Buyers planning travel via NH-44 will see the Jakh-Vijaypur-Kunjwani corridor reach 94.14% completion, yet the broader Delhi-Amritsar-Katra project faces delays and higher costs. The government revised the total budget upward to Rs 10,109.24 crore from Rs 8,457.14 crore, pushing final delivery dates to as late as November 2027 for some segments despite spending Rs 4,808.60 crore so far.
Key points
- The Jakh-Vijaypur-Kunjwani stretch (Package-XVI) has the highest progress at 94.14%.
- Combined revised cost of the four packages is Rs 10,109.24 crore, up from the original Rs 8,457.14 crore.