DHBVN wanted a new power system. Regulator said: keep BPTP's existing lines.
Buyers at BPTP Park 81 will receive electricity connections faster after the Haryana Electricity Regulatory Commission allowed the developer to keep its existing power grid. The regulator directed Dakshin Haryana Bijli Vitran Nigam to energize the current substation and release pending connections within 30 days.
Key points
- HERC permits BPTP to retain its 11 kV network at BPTP Park 81, Faridabad.
- BPTP must file a single-point supply electrification plan within 30 days; DHBVN has 30 days to respond, or it's deemed approved.